Swimming Pool

Status of work are as follows:

  • Work has started on 28/09/2013.
  • Completion period is six months.
  • The existing smaller pool of size 40m x 15m is being replaced by a new larger Olympic size pool of dimension 50m x 25m.
  • Depth of 1.2m at shallow end and 2m at deep end and a kids pool of size 15m x 6m with 600mm depth for training and swimming by small children.

Image 1

Image 2

Laying of foundation stone by Director of IIT Delhi on 24/10/2013